Lead Times:
-
March 2011 lead times decreased slightly when compared to February 2011.
-
Average lead time was 10.6 weeks.
-
Lead times continue to be significantly lower than mid-2010, when we saw a high average lead time of 17.2 weeks.
-
Manufacturers with higher-than-average lead times in March included:
o Vishay
o Fairchild
o Microchip
o NXP
o Altera
o ON Semi
o Atmel
o Maxim
o Microchip
-
We expect lead times to continue to adjust as more information becomes known about the longer term effects of the Japanese earthquake and tsunami.
|
Stock Availability:
-
We estimate on average 2.1% of quotes had lead time quoted.
-
This percentage is down slightly from February 2011.
-
The manufacturers we observed with the highest percentage of lead time quotes in February included:
o Linear Tech
o Microchip
o Maxim
 |
|